CONTRACT ADMINISTRATION PHASE
The Designer will visit the Project premises as deemed necessary by the Designer, or as otherwise agreed by the Designer in writing, to become generally familiar with the progress and quality of the Work and to determine in general if the Work is proceeding in accordance with the Contract Documents. The Designer will visit the premises a minimum of one time per week. However, the Designer shall not be required to make exhaustive or continuous inspections at the Project premises to check the quality or quantity of the Work. On the basis of such on-site observations, the Designer shall keep the Owner informed of the progress and quality of the Work, and shall endeavor to guard the Owner against defects and deficiencies in the Work of the Contractors.
Designer requests minimum of two meetings per month with Owner, Contractor, Construction Project Manager, and Designer to discuss Project progress. At least one of which will be attended by the Owner in person and one of which the Owner may participate by phone. |